The Senate, on Tuesday, threw its weight behind the $2billion future investments plan by the biggest thermal plant in Sub-Sahara Africa, Egbin Power Plc.
The Senate Committee on privatisation and commercialisation, which declared this during a facility visit to the plant in Ikorodu Lagos, maintained that the plant has “done well” in justifying October 1, 2013 power sector’s privatisation by the federal government.
Chairman of the committee, Senator Theodore Orji, who led the delegation that included Deputy Chairman of the committee, Senator Adelere Oriolowo; Senator Issa Jubril; Mr Saibudeen Oduniyi; Clark of the Committee, Abdullai Sadiah, queried the transmission and gas constraints, which have downed the power distribution below generation capacity.
Noting that Egbin is “doing fine” with its post-privatisation investments and activities, Senator Orji stated that the plant, which has invested about $1billion in the last seven years, should be encouraged to do more.
“This is a fact-finding mission about the power privatisation. We are encouraged by what we have seen at Egbin and we shall go back to the Senate to give our report on the entire process.
“I can say that you are trying your best. You are doing fine and you should be encouraged to do more in terms of investments,” he said.
Director, Egbin Power Plant, Mr. Kola Adesina, declared that the plant, which has invested $1 billion in its value chain, is perfecting investment plan of $2billion for expansion.
Adesina who is also the Group Managing Director of Sahara Power Group, gave the breakdown to include $1.8 billion for Egbin Power 2 and overhaul of the existing plant as well $200 million for estate (quarters).
“The plant, which is the biggest in Sub-Sahara Africa with capacity of 1350MW was generating 400 MW as at the time we took over, but today the generation has been surged above 800MW. At some points, we generated 1,100MW. We have been doing an average of 1,000MW this year.
“We are having a future investment including the Egbin 2 expansion, overhauling of Egbin 1 and staff quarters that will cost $2 billion.
“Despite these, there are challenges we face that we want this Committee to help us with. The NBTE still owes Egbin a debt of N388 billion including money for actual energy wheeled out, and interest for late payment.
“There is a challenge of gas constraints which cost us 106.34MW since June 2020 due to these external constraints. In 2021 alone, we have lost N13.68 billion to these external constraints.”
Stating that his company would stop at nothing to help the Nigeria’s course for power supply improvement, Adesina, noted that Sahara Group, owner of Egbin, has also invested in distribution stratum of the power industry through the Ikeja Electric.
“We made an investment of $1 billion in total for the generation and the distribution because we know that there is a need for a handshake between the generation and distribution. An average Nigerian doesn’t understand what Megawatt mean. What he or she understands is to press his or her switch and the bulb is lighted.
“We are of the belief that Nigeria deserves better. We cannot understand why the country with over 200 million people will still be generating about 4 000MW. As Nigeria is struggling with this 4,000MW, Korea is generating 120,000 MW per day.”
YOU SHOULD NOT MISS THESE HEADLINES FROM NIGERIAN TRIBUNE
Senate backs Egbin Power’s $2bn fresh expansion investments
We Have Not Had Water Supply In Months ― Abeokuta Residents
In spite of the huge investment in the water sector by the government and international organisations, water scarcity has grown to become a perennial nightmare for residents of Abeokuta, the Ogun State capital. This report x-rays the lives and experiences of residents in getting clean, potable and affordable water amidst the surge of COVID-19 cases in the state. Senate backs Egbin Power’s $2bn fresh expansion investments