The Transmission Company of Nigeria (TCN) has announced the full restoration of the national grid after a fire accident which occurred at the Afam Power Generating Station earlier on Monday, April 15, 2024.
A statement signed by the General Manager, Public Affairs, TCN, Ndidi Mbah, and made available to Tribune Online, said the fire caused a partial disturbance of the national grid.
The TCN, however, pledged its continuous investment in measures that will strengthen the grid infrastructure.
“The Transmission Company of Nigeria (TCN) announces the full restoration of the national grid following a fire incident at the Afam power generating station, which caused a partial disturbance of the nation’s grid.
“At 02:41Hrs today, 15th April 2024, a fire erupted at the Afam V 330kV bus bar coupler, leading to the tripping of units at Afam III and Afam VI. This resulted in a sudden generation loss of 25MW and 305MW respectively, destabilizing the grid and causing a partial collapse.
“During the incident, the Ibom Power plant was isolated from the grid and was supplying parts of the Port Harcourt Region. This further minimized the effect of the system disturbance. TCN confirms that the affected section of the grid has been fully restored and stabilized.
“TCN reaffirms its commitment to enhancing the resilience and reliability of the national grid and pledges to continue investing in measures aimed at strengthening the grid infrastructure,” the statement concluded.