The Transmission Company of Nigeria (TCN), Enugu Region, has commissioned a new 75MVA 132/33kV power transformer at its Mile 50 Abakaliki Transmission Substation in Ebonyi State.
The commissioning has boosted the substation’s capacity to 135MVA, enhancing its wheeling capacity and enabling increased bulk power supply to the Enugu Electricity Distribution Company for distribution to Ebonyi State and parts of Cross River State.
ALSO READ:TCN, Lagos govt partner to protect transmission facilities
The General Manager (Transmission), Enugu Region, Dr. Thomas Inugonum, revealed that TCN has approved the procurement of a new 60MVA power transformer to replace a decommissioned leaking unit, which will add 48MW to the substation’s capacity upon completion.
He added that the transformer project is part of the ongoing TCN–World Bank power projects aimed at further enhancing power supply in Nigeria.
WATCH TOP VIDEOS FROM NIGERIAN TRIBUNE TV
- Relationship Hangout: Public vs Private Proposals – Which Truly Wins in Love?
- “No” Is a Complete Sentence: Why You Should Stop Feeling Guilty
- Relationship Hangout: Friendship Talk 2025 – How to Be a Good Friend & Big Questions on Friendship
- Police Overpower Armed Robbers in Ibadan After Fierce Struggle