Lekki Deep Sea Port at 81% completion ― ICRC

Published by

The Infrastructure Concession Regulatory Commission (ICRC) says the Lekki Deep Sea Port project is now over 80 per cent completed.

According to the ICRC, “although it was widely reported across several media outlets that the project is at 96 per cent completion, the Commission wishes to clarify that the project is at 81.14 per cent completion.”

In a statement issued Wednesday in Abuja, Manji Yarling, Acting Head, Media & Publicity, ICRC said a breakdown of the completion status shows that: “dredging and reclamation are at 90.93%, Quay Walls at 87.3%, Breakwater at 82.74% and Landside Infrastructure at 70%, bringing to a total of 81.14%.”

The spokesperson noted that as regulators of all concession agreements entered into by the Federal Government of Nigeria, “ICRC deems it imperative to clarify this information and present the correct figure.

“The Concessionaire, Lekki Port LFTZ Enterprise Ltd, is working round the clock to ensure the project is completed on schedule – The project is expected to be completed in September 2022 and become operational in December 2022.”

On its part, he affirmed the ICRC will continue to carry out its regulatory function to ensure that the project, like all other government concessions yield the desired value for money, profitability, efficiency, economic growth, job creation and other gains for which the contract was entered into.

The Lekki Deep Sea Port project is a 45 years concession by the Nigerian Ports Authority (NPA) awarded on a Build, Own, Operate and Transfer (BOOT) Public-Private Partnership (PPP) model.

Upon completion, Lekki Port will have a total of 3 container berths, 1 dry bulk berth and 3 liquid berths.

YOU SHOULD NOT MISS THESE HEADLINES FROM NIGERIAN TRIBUNE

We Have Not Had Water Supply In Months ― Abeokuta Residents

In spite of the huge investment in the water sector by the government and international organisations, water scarcity has grown to become a perennial nightmare for residents of Abeokuta, the Ogun State capital. This report x-rays the lives and experiences of residents in getting clean, potable and affordable water amidst the surge of COVID-19 cases in the state…Lekki Deep Sea Port  Lekki Deep Sea Port

Selfies, video calls and Chinese documentaries: The things you’ll meet onboard Lagos-Ibadan train

The Lagos-Ibadan railway was inaugurated recently for a full paid operation by the Nigerian Railway Corporation after about a year of free test-run. Our reporter joined the train to and fro Lagos from Ibadan and tells his experience in this report…Lekki Deep Sea Port  Lekki Deep Sea Port

Recent Posts

How I combined Navy job with content creation – Cute Abiola

Abdulgafar Abiola, also known as Cute Abiola, has shared his experiences juggling his career in…

6 minutes ago

How I handled a church member’s correction — Sam Adeyemi

“The next day, a church member sent a text message to Pastor Nick and said,…

9 minutes ago

PDP is sick, will take time to heal — Ex-Benue gov, Suswam

“For now, I would say that PDP, yes, is in the hospital, is in ICU…

12 minutes ago

Don’t sleep, your enemies aren’t — CDS tells troops in Northwest

"The battle you are fighting is [not] just one. Don’t sleep, because your enemies are...

25 minutes ago

We must play our roles to see Nigeria of our dream — Obasanjo

Former Nigerian President, Chief Olusegun Obasanjo, has called on every Nigerian to play his role…

31 minutes ago

Nissan to cut 11,000 more jobs, shut seven factories amid slump in sales

Japanese automaker Nissan has announced plans to cut an additional 11,000 jobs worldwide and shut…

37 minutes ago

Welcome

Install

This website uses cookies.