NPA’s seizure of 156 million euros power equipment stalls 245MW plant

Published by

Officials of the Ministry of Power have told the Senate Committee on Power, Steel Development and Metallurgy, headed by Senator Enyinnaya Abaribe, that vital equipment meant for the completion of the 245 megawatts Kaduna Power Plant are rotting away in Onne Port, Rivers State since 2015.

The Senate Committee, which was on tour of the power installations in Kaduna, was also informed that the 156 million Euros (about N54billion) power plant which should have been completed since 2014 had remained in limbo due to repeated tango with port authorities among other issues.

Director of Distribution at the Ministry of Power, Priscilla Sapke, who briefed the Senate Committee during the tour of the power station said that repeated appeals to the Nigerian Ports Authority (NPA) and other agencies in Onne, Rivers State, had fallen on deaf ears as the port had seized 19 containers said to contain accessories critical to the completion of the Kaduna Power Plant.

Sapke said that several containers were initially seized by the port authorities between 2012 and 2014 but that a number of the containers were released to General Electric and Rockson Engineering, contractors to the plant on payment of 50 per cent of an agreed demurrage while 19others have been lying at the Onne Port since 2015.

She did not give details of the exact amount paid by the companies.

She said, “The directive is that they (the Port) should release government’s goods and talk later about commercial issues but they refused.”

As a result of that refusal, the project meant to last 24 months now has no definite date of completion.

The Dual Fired LPFO/Gas 215 MW Kaduna Power Plant was initiated in 2009 and initially meant to be completed in 2011, but the shift in the original location at Kakuri in Kaduna Metropolis to the current location at Kudeda was said to have necessitated the change in the completion date.

Officials of General Electric and Rockson Engineering, who were also on hand, told the Senate committee that the project could come on stream in November this year if the seized equipment were released.

Besides the 215 megawatts plant, the Gurara Dam is also expected to supply 30 megawatts to the power plant to take its capacity to 245 megawatts.

Chairman of Senate Committee on Power, Senator Enyinnaya Abaribe, who led 10 other Senators on the tour said that the Senate was disappointed that the completion date of the power installation remains uncertain years after it was initiated.

He said, “The Committee is not very pleased at the cost overrun and the time overrun. This is a project that should have been completed years back but we are not even sure when it will be completed because some of these also infringe on cost components and our worry is for the Nigerian public who are going to pay for this.

“We are not pleased that if we are not careful we may end up getting a white elephant project from this.  Whatever this committee needs to do to get this project completed, we are ready to do.

“We will be interacting with the Minister of Power and also with his counterpart in the Ministry of Water Resources, because the Gurara Dam is also part of the problem.”

Recent Posts

Oyo govt appoints Ladoja as chairman, 2025 World Egungun Festival

He said the World Egungun Festival remains a significant cultural showcase that draws participants and…

16 minutes ago

Tinubu’s second anniversary: Wike announces two-week project commissioning schedule

Wike said the projects to be inaugurated cut across the Abuja city centre, the satellite…

41 minutes ago

Police arrest 17 suspected killers of NDU graduates in Bayelsa

A source confirmed that the arrest of the suspected killers cultists was made possible by…

1 hour ago

5 Best Altcoins for Next Bull Run Backed by Strong Developer Activity 

What if the next breakout moment isn’t months away, but already unfolding? With Chainlink whales…

1 hour ago

Regional devt commissions, step towards restructuring — Gbenga Daniel

Speaking, the former governor of Ondo state, Dr Olusegun Mimiko, stressed the urgent need to…

1 hour ago

Power supply: Band A customers in 557 streets to get compensation from DisCos

The NERC ordered that the affected DisCos implement the compensation through either...

1 hour ago

Welcome

Install

This website uses cookies.