Lagos State Governor, Babajide Sanwo-Olu
Lagos State governor, Mr Babajide Sanwo-Olu, on Tuesday flagged-off activities marking the commencement of construction of the final phase of the Blue Line Rail Project, promising its completion next in 2021.
This was just as the integrated mass transportation initiative of the state government recorded a huge progress with the successful completion of an elevated sea-crossing track of the Lagos Blue Line Rail Mass Transit project as Governor Babajide Sanwo-Olu led his exco members to inspect and inaugurate it.
The 5-kilometre long Continuous Beam Bridge constructed from Iganmu to Marina is part of the 4th phase of the Blue Line Rail Line Project.
Speaking at the event, the governor said the completion of the sea-crossing track indicated his administration’s commitment towards completing the state-funded rail project started in 2009, and its resolve to reduce the travel time through an effective and efficient intermodal transport system and also key to the building of a 21st Century economy for Lagos.
According to him, “The completion of this project is top priority for our administration, as it is critical to the achievement of our prioritised pillar of traffic management and transportation in our six-point development agenda, known as project THEMES.
“The aim of this rail project is basically to reduce the travel time through an effective and efficient intermodal transport system. It is also key to the building of a 21st Century economy, which is central to the vision of a Greater Lagos aspiration. We are committed to delivering this project next year and ensuring its operation starts in 2021.”
The construction of the Blue Line rail tracks, Sanwo-Olu noted, was being implemented in strict adherence to the State’s Strategic Transport Master Plan, which prescribes six rail lines and one monorail for the long-term strategic goals of the state.
Apart from the Blue Line, Governor Sanwo-Olu disclosed that his administration would be starting the construction of the Red Line Rail Project from Agbado to Marina, pointing out that advertisement had been published in the media to invite investors for the construction of four other rail lines under a Design, Build, Operate, Maintain and Transfer model of Public-Private-Partnership arrangement.
The governor said the advertised rail projects include the 68-kilometre Green Line, 60-kilometre Purple Line, 34-kilometre Yellow Line and 48-kilometre Orange Line.
According to him, the Green Line will start from Marina through Victoria Island, Lekki Phases 1 and 2, Ajah, Ogombo, Lekki Airport to Lekki Free Trade Zone, while the Purple Line is expected to start from the Redemption Camp going through Ogba, Iyana Ipaja, Igando and terminating at Ojo.
“The Yellow Line will stretch from Otta through Isheri Osun, Ejigbo Mafoluku, Isolo to the national theatre, and the Orange Line will span from Ikeja moving through Mile 12, Ikorodu, Alapadi, Eligana, Isiwu, Imota and terminating at Agbowa,” he said.
“The Government will also start the construction of eight quality bus corridors in strategic areas of Lagos. These bus corridors is our government’s initiative aimed at giving dedicated road space and traffic signal priority to mass transit buses in order to reduce journey times and improve service consistency.
“The aim of the initiative is to encourage people to change from cars to buses and thus reducing traffic congestion. We are opening up new transport corridors to organised transport operators for seamless transport connectivity, reduce congestion and truly make our state competitive,” he added.
Governor Sanwo-Olu congratulated the Lagos Metropolitan Area Transport Authority (LAMATA) and the contractor, China Civil Engineering Construction Company (CCECC) for the progress, urging them to complete the Blue Line rail project on record time.
CCECC Managing Director, Mr Michael Chiang, said the Continuous Beam Bridge represented the most complex construction work on the Blue Line Project and a milestone, noting that the engineering firm encountered several geological challenges before completing the sea-crossing section.
ALSO READ:We generated over N45bn from stamp duties ― NIPOST
He said: “It is another great milestone for the project, which indicates that we have successfully overcome the major difficulties and solved the most complex construction section problems.
“We have overcome different challenges ranging from the impact of fluctuating tides, the frequent berthing of oil vessel, the very complex geological condition of the seabed and several incidents of barges colliding with the trestle near the busy sea navigation route.”
Also, the Managing Director of LAMATA, Mrs Abimbola Akinajo, described the feat as a “great milestone,” saying the ceremony marked the successful completion of 85 per cent of Phases One to Four of the Blue Line Project, which spans from Mile 2 to Marina.
In life and even in death, Pa Samuel Ayodele Adebanjo remained a man of the…
With lack of access to career counseling and advisory largely contributing to unemployment in Africa,…
CONTINUING efforts to fulfil its mandate through strategic collaborations, the National Troupe of Nigeria (NTN)…
A few days ago, the Federal Inland Revenue Service (FIRS) ordered all banks in the…
A group christened 'Lawyers for the Cause of Bauchi (LAWBA)' has decried the "selective, partial…
A group known as 'Forum of Ayatutu Professors' in Benue State on Saturday called for…
This website uses cookies.