FULL LIST: New gas infrastructure projects to be commissioned by Tinubu

The federal government announced on Friday that the President, Bola Ahmed Tinubu, will soon commission three critical gas infrastructure projects being undertaken by the Nigerian National Petroleum Company Limited (NNPCL) and partners.

The President’s Special Adviser on Media & Publicity, in the statement, explained that the implementation of the projects is in line with his commitment to significantly leverage gas to grow the economy, adding that the projects support the federal government’s effort to grow value from the nation’s gas assets while eliminating gas flaring.

Here’s a list of the three projects as contained in the statement by the Presidency.

“(1) AHL Gas Processing Plant 2 (GPP – 2) – 200mmscf/d

This project is an expansion to the Kwale Gas Processing Plant (GPP – 1), which currently supplies about 130MMscf/d of gas to the domestic market. The processing plant is designed to process 200MMscf/d of rich gas and deliver lean gas through the OB3 Gas Pipeline. This additional gas supply will support further rapid industrialization of Nigeria. The plant will also produce about 160,000 MTPA of Propane and 100,000 MTPA of Butane, which will reduce the dependency on LPG Imports. The AHL Gas Plant is being developed by AHL Limited, an incorporated Joint Venture owned by NNPC Limited and SEEPCO.

ALSO READ: Shell signs agreement to build gas pipelines in Oyo

“(2) ANOH Gas Processing Plant (AGPC) – 300MMscf/d

The ANOH gas plant is an integrated 300MMscf/d capacity gas processing plant designed to process non-associated gas from the Assa North-Ohaji South field in Imo State. The plant will produce dry gas, condensate, and LPG. The gas from ANOH gas plant will significantly increase the domestic gas supply, leading to increased power generation and accelerated industrialization. The ANOH Gas Plant is being developed by ANOH Gas Processing Company, an incorporated Joint Venture owned by NNPC Limited and Seplat Energy Plc on a 50-50 basis.

“(3) ANOH-OB3 CTMS Gas Pipeline Project

“The project involves the engineering, procurement, and construction of 36”x23.3km ANOH-OB3 Project. The Transmission Gas Pipeline will evacuate dry gas from the Assa North-Ohaji South (ANOH) primary treatment facility (PTF) to OB3 Custody Transfer Metering Station (CTMS) for delivery into the OB3 pipeline system. About 600MMscf/d is estimated to be available from two separate 2 x 300MMscf/d capacity gas processing production trains from AGPC & SPDC JV.”

Adegbite Taoheed

Recent Posts

BBNaija S10: Organisers announce audition dates

Organisers of the Big Brother Naija (BBNaija) reality show have officially announced the audition schedule…

10 minutes ago

FG developing framework on responsible use of AI — Information Minister

The federal government says it is developing a national policy framework on the responsible use…

20 minutes ago

Bauchi gov inspects construction of international conference center project

Bauchi State Governor, Senator Bala Abdulkadir Mohammed, on Saturday paid an inspection visit to the…

25 minutes ago

Bauchi gov inspects construction of International Conference Center project

Bauchi State Governor, Senator Bala Abdulkadir Mohammed, on Saturday, paid an inspection visit to the…

27 minutes ago

Center launches initiative to combat GBV, SEAH in Osun communities

The Centre for Gender, Women, and Children in Sustainable Development (CGWCSD) has launched an initiative…

29 minutes ago

PDP wants intending defectors to leave before national convention

•Keen to deny them role in leadership new selection AS the Peoples Democratic Party (PDP)…

2 hours ago

Welcome

Install

This website uses cookies.