The Transmission Company of Nigeria (TCN), Enugu Region, has commissioned a new 75MVA 132/33kV power transformer at its Mile 50 Abakaliki Transmission Substation in Ebonyi State.
The commissioning has boosted the substation’s capacity to 135MVA, enhancing its wheeling capacity and enabling increased bulk power supply to the Enugu Electricity Distribution Company for distribution to Ebonyi State and parts of Cross River State.
ALSO READ:TCN, Lagos govt partner to protect transmission facilities
The General Manager (Transmission), Enugu Region, Dr. Thomas Inugonum, revealed that TCN has approved the procurement of a new 60MVA power transformer to replace a decommissioned leaking unit, which will add 48MW to the substation’s capacity upon completion.
He added that the transformer project is part of the ongoing TCN–World Bank power projects aimed at further enhancing power supply in Nigeria.
The President of the Dangote Group, Alhaji Aliko Dangote, and the former Central Bank of…
Lagos State Governor, Babajide Sanwo-Olu, made a surprise appearance on the runway at the 2026…
The Independent National Electoral Commission (INEC) has reconfirmed suspected manipulation of its voter registration system…
The Founder and Presiding Bishop of Victory International Church, Bishop Taiwo Adelakun, has stressed the…
Minister of Works, David Umahi, has dismissed Peter Obi’s presidential ambition, questioning the former Anambra…
The African Democratic Congress Presidential Campaign Council (ADC-PCC) has said the attempt by the All…
This website uses cookies.