TCN explains collapse of national grid

Published by

The Transmission Company of Nigeria (TCN) said the collapse of the National Grid on May 8, at 2:32p.m, was caused by multiple tripping on its substation in Onitsha, Anambra.

The Managing Director of TCN, Mr Mohammed Usman, made the disclosure at a news conference in Abuja on Friday.

The national electricity grid had on Wednesday, experienced some disturbances resulting in a reduction of electricity allocation to electricity distribution companies in the country.

Mohammed also said that the collapse may also have been triggered because one of the generators went off.

“What happened a day before yesterday at 14;32 hours was a case of system collapse, we had tripping.

“The reason for the grid collapse was that there was multiple tripping around Onitsha substation. We are also suspecting that one of the generators went out.

“We have sent our team of engineers to go and investigate, we normally investigate this kind of disturbances,’’ he said.

He, however, said that in spite of the fragile nature of the nation’s power grid, TCN had achieved some level of stability on the national grid.

“Although, we have achieved some level of stability on the grid through the massive investment that we have done in the last two years.

“It does not mean that our grid has become disturbance-free because our grid is still very fragile. It is a journey that we are in that will take us to have a modern and stabilised grid.

“You remember, I had told you that we need to achieve four important things to have a stabilised grid.

ALSO READ: Electricity consumers to get prepaid meters 10 days after payment ― NERC

“We need to have a critical investment in lines and substations so that we put N-1 across the country, that will ensure that any equipment that goes out at any point in time will not affect supply on that area.

“For example, what happened in Apo recently, where we had a transformer that got burnt, we restored supply in two hours, because we had N-1 in that substation and that is what we are trying to achieve in all the country,” he said.

He said the company had raised 1.6 billion dollars for investment in lines and transmissions saying that attainment of the required investments in transmission would take some time.

“It is not what we will do in one day; the investment project for northern corridor transmission project, we just advertised; the one for Abuja, transmission project, we just signed, the one for Lagos and Ogun transmission project, we are about to launch the procurement process.

“The one for World Bank, we just launched the project, but the equipment has not arrived, so we are on a journey,’’ he said.

Mohammed said that there was an urgent need to have a functional SCADA in the power sector to monitor activities on the national grid.

“If we have a functional SCADA, it will show clearly what happened on the grid, and that is why we in TCN, deployment of SCADA is not an option, we have to deploy it.

“Because for us to have a modern grid you need to have a functional SCADA for the management of the grid,’’ he said.

He said there was also an urgent need to have a commensurate investment on the distribution chain to ensure a stable grid in the country.

Recent Posts

10th Anniversary: Contribute positively to Akure’s devt — Deji charges indigenes

He described the present administration in the state as a “Friend of Akure” and commended…

2 minutes ago

‘Missing N6trn’: SERAP drags FG to ECOWAS Court over unpublished NDDC audit

They are further seeking an order compelling the publication of the audit report and demanding…

22 minutes ago

Why Peter Obi must get security clearance before entering Edo — APC chair

The Edo State chapter of the All Progressives Congress (APC) has reiterated that Labour Party’s…

2 hours ago

Hawaii monitors Tsunami risk following major quake off Russian coast

Hawaii was placed under a tsunami watch on Saturday after a magnitude 7.4 earthquake struck…

2 hours ago

Anambra South by-election: Azuka Okwuosa wins APC senatorial ticket

Azuka Okwuosa defeated Dr. Obinna Uzor to clinch the APC ticket.

3 hours ago

Astronomer CEO resigns after viral Coldplay ‘kiss cam’ video

The CEO of New York-based software firm Astronomer, stepped down after being caught on camera…

3 hours ago

Welcome

Install

This website uses cookies.